Hi PmArtK,
Oddly enough, I still see the exact issue in Project 2010. The Work Incomplete filter does not seem to work correctly it is applying the criteria to the resources, not to assignments.
As a suggested work around, change the Resource usage view and add start, finish fields to the table. Print the left side of the view only by dragging the split bar far right.
I hope this helps.
Julie