ok...here is the situation...I have a PDC and a BDC...that need to be upgraded to win2K, the PDC ids alos getting a new RAID controller and Hard drives...I want to retain all user accounts, hence the "upgrade" path....this is my plan...run a backup of the sam DB and other important folders, and create an ERD...turn off the BDC...run an upgrade on the PDC.....rebuild the BDC from scratch to win2k and have it sync up with the upgraded PDC....turn off the PDC install the new drives and rebuild the PDC from scratch with win 2k....Is that the correcvt approach to this situation