Can you give me the reference to the web page? I am running Project 2010 SP-2 with the April 2014 CU. I can edit the field in both a manually scheduled or autoscheduled task. Ah, wait. Have you disabled splitting tasks? Check File > Options, Schedule and make sure the option "Split in progress tasks" is enabled (checked). It is by default.