We did it a little differently. We coded a function in Access to open the project file, export to Excel format, then import to a table in Access. We looked at using an mdb format instead, but we couldn't get Project to save the Project tables as mdb format, whereas we did get that to work (using an export mapping) to an Excel format. If I remember, Project didn't want to give is the data the way we wanted it when we saved to mdb. You may want to play with the methods, depending on what data you want, and how you want to see it.
Our process has been working great for almost a year now. One button processing.
Regards;
Mark
Mark
<O>
_|_