INTELLIGENT WORK FORUMS
FOR COMPUTER PROFESSIONALS

Log In

Come Join Us!

Are you a
Computer / IT professional?
Join Tek-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Tek-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

How obtain accurate total of hours estimated of all subtasks that are a certain type?

How obtain accurate total of hours estimated of all subtasks that are a certain type?

How obtain accurate total of hours estimated of all subtasks that are a certain type?

(OP)
How obtain accurate total of hours estimated of all subtasks that are a certain type?

We have a project plan and of course there are many tasks with subtasks underneath each task

Example:
Task Estimated Work Hours Actual Work Hours Task type

Overall Project

Data entry screen 32 14
Define Requirements 8 5 Requirement
Write Specification 8 6 Spec
Perform Coding 8 3 Coding
Conduct Testing 8 0 Testing

+Reporting 40 24
Define Requirements 16 15 Requirement
Write Specification 8 6 Spec
Perform Coding 8 3 Coding
Conduct Testing 8 0 Testing


Question: When we perform a filter on the TASK TYPE column and select "Spec" WE STILL have the same total of hours (32,24 respectively) at the task level and even at a roll-up project level..
We want to determine how many hours total are "Spec" related for these 2 tasks.

Any way to do this without exporting it to Excel or without adding up the columns manually that have the word "Spec" in that column?

Thank you
Peter

RE: How obtain accurate total of hours estimated of all subtasks that are a certain type?

(OP)
When I did a group by Text1 which is the Phase Type field it did sum up the type but lost the task name. I would like the type summed up by each task. Not sure how to do this. Apologize for my newbie question. Here is what happened....
I put the file at www.peterbio.com/tempit

So I am looking to show the total hours for the type "spec" by each task with the task name listed. I have a 700 line project plan.
Thanks
Peter

RE: How obtain accurate total of hours estimated of all subtasks that are a certain type?

See my reply at the MSOffice forums.

RE: How obtain accurate total of hours estimated of all subtasks that are a certain type?

(OP)
Thank you so much, it worked!!
Peter

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Tek-Tips Forums free from inappropriate posts.
The Tek-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Tek-Tips forums is a member-only feature.

Click Here to join Tek-Tips and talk with other members! Already a Member? Login

Close Box

Join Tek-Tips® Today!

Join your peers on the Internet's largest technical computer professional community.
It's easy to join and it's free.

Here's Why Members Love Tek-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close