INTELLIGENT WORK FORUMS
FOR COMPUTER PROFESSIONALS

Log In

Come Join Us!

Are you a
Computer / IT professional?
Join Tek-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Tek-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

MSQ740 MS Project Import

MSQ740 MS Project Import

MSQ740 MS Project Import

(OP)
We have a user who is exporting MSQ740 data to MS Project and updating it.  We run Ellipse via Citrix Client, which has a time out set to disconnect the user after a stated period of time.  Ellipse is left running in the background.  The issue is that the user frequently gets pulled away from his desk and eventually, when he does return, Citrix has timed out and he cannot import the info that has been changed on the MS Project file.  Has anyone else had this experience? I do not know of a way to save the project, make mods, re-import and update at a later time???  Does anyone know how the new Work Manager in Ellipse 6 handles this?  

RE: MSQ740 MS Project Import

Hi, I am a new user of Ellipse, and I am want to export data from MSQ740 to MS Project. Do you have some information about that?, may be a web address.

Thanks a lot.

RE: MSQ740 MS Project Import

Hi.. if you got time-out problem in any MSQ programs..

Just click on :
- the top bar 'Tools'
- then Options
- then go to Timeout tab
- change timeout period

Have fun

RE: MSQ740 MS Project Import

This problem exists at all sites that run MSQ740-MSProject in a Citrix environment. And, SOX requirements are making it worse. Citrix lacks the ability to "keep alive" a COM connection between 2 hosted apps that are idling.

The most promising solution is to create an MSProject macro that "remembers" the input details it received: Ellipse User ID, District, Position + Work Group and Schedule Date. Then, Ellipse could be re-inititated from MSProject, re-starting msq740 at the appropriate place, and presenting the user with an "Update Ellipse" button.

I'll give that a shot over the holidays and let you know how it goes.

GM2

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Tek-Tips Forums free from inappropriate posts.
The Tek-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Tek-Tips forums is a member-only feature.

Click Here to join Tek-Tips and talk with other members! Already a Member? Login

Close Box

Join Tek-Tips® Today!

Join your peers on the Internet's largest technical computer professional community.
It's easy to join and it's free.

Here's Why Members Love Tek-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close