MS Projects 2003.
I have a task with 10 subtasks underneath it.
The first three sub tasks have percent completes indicating the tasks are on schedule.
The remaining tasks are not scheduled to start.
The Summary Tasks progress bar indicates the group of tasks is behind schedule.
I would expect to see the Summary Task progress as equal to the on time schedules of the first three tasks until the the remaining tasks go into work.
Is there a way to show the Summary Task progression differently?
Thanks,
Ray
I have a task with 10 subtasks underneath it.
The first three sub tasks have percent completes indicating the tasks are on schedule.
The remaining tasks are not scheduled to start.
The Summary Tasks progress bar indicates the group of tasks is behind schedule.
I would expect to see the Summary Task progress as equal to the on time schedules of the first three tasks until the the remaining tasks go into work.
Is there a way to show the Summary Task progression differently?
Thanks,
Ray