Aug 22, 2006 #1 Tom540 Technical User Joined Aug 22, 2006 Messages 1 Location GB If i have a three day task, how can I set Resource A to day 1, Resources B and C to Day 2, and Resource D to day 3 or similiar? Thanks in advance
If i have a three day task, how can I set Resource A to day 1, Resources B and C to Day 2, and Resource D to day 3 or similiar? Thanks in advance
Aug 22, 2006 #2 PDQBach IS-IT--Management Joined Sep 26, 2003 Messages 1,523 Location US This is a homework question which isn't supposed to be posted to this group, but I'll answer it anyway. Create the resources Create the task Assign the resources to the task View | Resource usage and adjust as appropriate. Upvote 0 Downvote