I'm converting my departments MS projects over from '98 to 2000.

In the process I've updated a resource list project that list all potential resources, their user id, first and last name. All of these people are listed in order by their first name.

When converting the projects over, when clicking on 'Assign Resources,' it does show the right project to pick resources from, but it will also have listed at the bottom, people who are currently working on the project, and they are out of order, yet I have deleted them from that schedule.

Also, once I put them back in, it will still retain the previous percentage. For example: John Q Smith was 85% complete on this task. I delete him from the project and then bring him back in and it will still show him as 85%, even though I want to assign a new percentage to him.

I guess in the long run, is there any way to prevent MS Project from remembering all of these values?

thanks

 