MS Project 1998 linking recurring tasks

Status
Not open for further replies.

craigurai

Technical User
Sep 10, 2002
1
US
I am trying to link the end of a recurring task to another task using a finish to finish relationship. In other words, the goal is to anchor the starting point of the recurring task (meetings in this case) and then have the duration and amount of recurrences change based on the finish to finish linkage. When I tried to link the last meeting in a f-to-f, the 1 day task will move, but no more recurrences of the task will appear. Is this possible to do?
 