Hi everyone,
I've got a funny problem with the G/L setup options. It appears that every now and again, the G/L setup options for one of our company codes in Mas 90 3.71 are resetting themselves.
We find that the G/L year has changed to 2001, the period has changed to 6, the years to retain transaction and summary history change to 2yrs and the Auto Budget option changes from 'None' to 'Current.'
Everytime this happens, I reset the options as they should look but sometime later (could be a month, could be two days) it will reset back to the settings I posted above.
I have found, w/ the help of a colleague, that the sy0ctl file contains these exact settings that I listed above. Perhaps there is a program error occurring and Mas 90 takes these "Last known good values" from the sy0ctl file and applies them? Is that possible?
Has anyone had this problem, any ideas on how to resolve it?
I've got a funny problem with the G/L setup options. It appears that every now and again, the G/L setup options for one of our company codes in Mas 90 3.71 are resetting themselves.
We find that the G/L year has changed to 2001, the period has changed to 6, the years to retain transaction and summary history change to 2yrs and the Auto Budget option changes from 'None' to 'Current.'
Everytime this happens, I reset the options as they should look but sometime later (could be a month, could be two days) it will reset back to the settings I posted above.
I have found, w/ the help of a colleague, that the sy0ctl file contains these exact settings that I listed above. Perhaps there is a program error occurring and Mas 90 takes these "Last known good values" from the sy0ctl file and applies them? Is that possible?
Has anyone had this problem, any ideas on how to resolve it?