How do I assign equipment resources to a task without increasing the work that that task takes, while still taking advantage of work resource functions like load levelling and max units, etc.?
Could this not be as simple as the equipment needing to be a "material resource" and not a "work" resource? If you add the column "resource type" you should be able to change the equipment to "material" instead of "work". Not sure though.