Counting Tasks in MS Project

Status
Not open for further replies.

Krusher

IS-IT--Management
Jan 2, 2003
70
US
Does anyone know of a way to return a count of summary tasks (top level tasks) in MS Project? I wrote a VB macro to count active.selection, but I need a way to distinguish between summary and child level (indented) tasks. Many thanks in advance.
 


Hi,

I know next to nothing about MS Project. But VBA has some similarities between application.

Try counting tasks where the Parent of the task IS a task.

Skip,

[glasses] [red]Be Advised![/red] The Vinyards of Texas have produced a wine with diuretic dimishment and urethric relief...
Pinot More![tongue]
 