Having a very difficult time figuring this out.
Scenario - PRoject 2012
Create a task that has a DURATION of 20 days and WORK of 40 hours. This means I expect 10 hours of work to be done per week. I assign two resources. One at 25% and one at 75%. When I view the Resource Usage sheet I expect to see 2.5 hours per week for resource 1 and 7.5 hours per week for resource 2. THe Resource Sheet does not show this at all. It seems to screw it up all the time.
Am I even setting this up right?
There will be several tasks that will have work hours set over a longer duration with multiple resources at various percentages so I have to get this right.
Thanks!
Rick
Scenario - PRoject 2012
Create a task that has a DURATION of 20 days and WORK of 40 hours. This means I expect 10 hours of work to be done per week. I assign two resources. One at 25% and one at 75%. When I view the Resource Usage sheet I expect to see 2.5 hours per week for resource 1 and 7.5 hours per week for resource 2. THe Resource Sheet does not show this at all. It seems to screw it up all the time.
Am I even setting this up right?
There will be several tasks that will have work hours set over a longer duration with multiple resources at various percentages so I have to get this right.
Thanks!
Rick