Using MS Project 2000
I have created a filter that displays what I want to see in Project. I have figured out how to save as a web page using this filter. My only problem now is that I cannot figure out how to keep the data sorted by the start date in this saved web page. I think I need to...
Using MSproject 2000
When doing a "Save As" of a template "Filemname.mpp". Under File | Properties | Summary, the title takes on this new file name as the title. This is what I desire. But now I have created a template that will not behave in this way. Help! I don't understand how this...
Using Project 2000
I made a custom column to give indicators to show if a task is real late, running ahead, or almost on time.
I have set up the custom column as follows:
I have a formula: (now()-DateValue(Finish)).
I have graphic indicators set up as follows:
greater than 2 (red frown)
less...
Using Project 2000 (9.0.2001.0219 SR-1)
I work in a Job shop environment.
I have been managing a master schedule using a resource pool file. What I have been doing is making projects & inserting them into the master schedule & then unlinking the projects. Then I assign resources to the tasks...
I'm using Project 2000 SR-1.
I have a master project with about 40 inserted projects all using the same shared resource pool.
I recently had my resouce pool file get corrupted. Using my master project file I was able to sort of recreate a new resouce pool by copying resources into a new...