HI all:
I have 6 or 7 projects that share resources from a unique project (what I call the resources project). Sometimes I get random behaviours like:
I open project 1 (that opens the reosurces in the background) and from a different computer I open project 2 (also opens the resources), now if...
HI all:
Using Project 2003 Standard, how can I stop using a resource (e.g. he doesn't work with us any more?) I wouldn't like to delete him (I guess for history of the project), but how do I avoid that he gets selected for new projects?
Thanks!
HI all:
When using Microsoft Project 2003, I have a task A to which I assign a resource Peter (let's say I assign 40 hours for the following 6 weeks (everything OK upto there)
But we use the same project to "possible future" projects. These type of projects have a probability to happen, and I...
Hi all:
When using ptoject 2003, I have a task, with 2 resources assigned, with weekly timeline, I assign 40 hs each resource on certain week, so the task has 80 hs assigned, everything ok up to there
As soon as I assign another resource to this task, this resource gets automatically assigned...
HI there:
I have a very simple project in MSProject 2003.
I multiply Duration 1 (Budget hs) by Number 1 (Probability) to obtain Duration 2 (Probable Hours) and I use automatic calculation.
For some reason, after I close MS Project and then start the project again, it will stop calculating...