Hi,
This is probably anything but trivial, but consider this scenario:
I've got an Excel/CSV timesheet extract, with one line/entry "per date that someone does something on a task".
The excel field contains an identifier, let's call it "ERP Task ID". I have entered the same values on a text...
Hi,
Now here's a challenge...
Where I am, resource availability is scattered, ie. people are allocated to projects on and off for a few days at a time over the duration of the project. Entering this into the resource availability dialogue manually every time bookings are updated is error prone...
Hi,
I am scheduling a project with some workshops requiring travel. There is one day of travel before and after each workshop, and I have chosen to add the travel to the duration of the workshop for simplicity. This means that the total length of a workshop (to avoid weekend travel) is 3 to 5...
Hi,
In MS Project 2007, is it possible to create a custom field which summs the contents of a timephased field for the entire project duration? Specifically, I would like to create a ressource field showing the total of available hours per ressource.
The use scenario is as follows:
In my...
Hi,
I'd like to achieve the following:
1) Tasks require different skills, though never more than one skill
2) Resorces may posses any number of skills
3) Some tasks should only have ressources with matching skill assigned
4) Some tasks could have any ressource assigned
5) I'd like to view the...