Hi,
I want to run a status report everyday, to the status of each task, I can't find any field to show how many days the task is delayed even it is not finished. The situation is as the following :
baseline start day baseline finish day
Task AA - Day01...
Hi,
I want to have a column that can show how many days is really delayed while the task is even not finished yet. I try to use a duration1 and use the formula to calculate : Current Date - Baseline Finish Date, but it didn't work. Please help.
On the other hand, I would this figure show 0 if...
Hi,
I am using MS Project2003 Professional.
I inserted a some custom date field (date1, date2)
I found that if I didn't entry data to the cell, it will appear "NA", can I change it to appear nothing? or just a symbol "-" for easier reading?
On the other hand, is there any "condition...
Sometimes 2 task have dependency for Starting, and different dependency for finishing.
How can I solve this problem ?
Example :
Task A
Task B
Case 01:
A start, then B can follow to Start. (Start-to-Start)
A finish, then B can follow to Finish. (Finish-to-Finish)
Case 02:
A Start, then B...
Hi,
I really confuse how can I adjust the column width of the reports ?
for example :
http://www.geocities.com/bestchild10cc/mspjq02_a.jpg
I want to decrease the width of every column, but seems it cannot be set.
i am sorry for my idiot question.
Thanks for you kindly help.
Benson
Hi,
When I want to print a report eg. "Who Does What When", some of the work hours are too long, the report appear as xxxxx, I want to adjust the column width but I can't find, can anyone kindly so me?
Thanks.
Benson Poon