In a construction plan, i have a task
Start : 20.09.06
Finish: 28.10.06
Duration: 30d
Resources : material 1450, work 710h
so, actually :
start: 13.09.06
complete% : 2% for 20.09.06
if i enter the values of start date and %complete, ms project splits the task`s 2% part and keeps empty...