Is there a way to get MS Project to calculate the Early Finish (or any other finish date) given:
- % complete on tasks
- duration or work
- todays date
say that todays date is X (say 1st Sep). The task's duration is say 10 days. It is 40% complete. I would like to see the Early Finish...