Is there some equivalent of object grouping for tasks in Project 2000?
I have a series of tasks, each with the sub-task "Design", which is not the exact same sub-task, but rather a different instance of the same tasks that may occur at a different time and have a different duration. But, I may...
I'm trying to do something similar, except that the fixed date I have is in the middle of the project. I want to schedule backwards from that task for predecessor tasks, and forwards from it for descendant tasks or whatever they're called. Here's a detailed description of what I'm trying to do...