I have stumbled on an interesting issue and hope someone can help. I am using MS Project 2003 Standard. In my schedule, I have milestone tasks that are on the critical path and the text is black. The diamond in the Gantt is red. I looked in the Text Styles menu for "Critical Milestone" so I can...
I am having an issue with the Task Usage view. Hopefully someone can give me some guidance.
Normal operation of Task Usage:
When I select the Task Usage view, the "All Tasks" filter is used. All the tasks that are resource loaded display the resources and hours against each task in the entire...