Is there anyway I can update/show my work complete in hours/days rather than %? I am using Project 2002.
I have a number of tasks, fixed duration, with a number of resources assigned. Ideally I would like a way of flagging/reporting that based on the current date I have x hrs planned remaining...
Can anyone help? I am trying to create a report in project 2002 that shows the number of work hours planned, per resource, per month by task name, until the end of the project. I am not very familar with the report function in project and any suggestions would be very much appreciated.
Thanks
I have a programme showing a number of projects with people assigned to tasks from a resource pool. their hours predicted / worked are then entered into the task usage view generating the gantt chart view.
i would like to know if there is anyway of taking the information in the resource usage...
Our Timesheet management system can export reports mirroring the task view into excel (.csv) format. Does anyone know if or how I can then map or import this information into the task usage view of project 2002?
Thanks in advance.
Hi, Can anyone help me - Microsoft Project is causing me grief!
I am trying to plan and track the workload of a number of small
projects and the time of around 30 people. I want to run the project using hours so that planned time
can be compared to subsequent weekly timesheet information...