I am in "teach myself Project" mode and have encountered a problem that has me perplexed.
I created a custom calendar for the project, cleverly called "Proj Calendar". This calendar defines Mon-Sat as work days. Mon-Fri work 10 hrs, 8-12, 1-5, 7-9. Sat works 8-12 and 1-5. Sunday is off...