I received an answer to this offline that I thought I would share. Updates to assigned tasks are sent to you via email. You evidently have to open the update and close it again for the task in your task list to be updated.
Does anyone really assign and track tasks using Outlook's task list? It strikes me as a potentially powerful managment tool, but when I assign tasks...
1. updates only come via email. The assigned task itself is never updated.
2. the updates that come via email are too vague to be useful. For...
Has anyone ever tried to synchronize tasks on a project schedule (in MS Project) with tasks in Outlook? It strikes me as a powerful tool. Since you can associate resources in Project with domain accounts, domain accounts are associated with Exchange accounts and you can assign Outlook tasks to...